Progress Updates As of December 3, 2024

  • Paving Upgrades at Allenwood Elementary School

    • Awarded to Catel Inc
    • Construction: July 2023 – October 27, 2023
    • Construction Update:
      • Punch List work in progress. 

    Paving Upgrades at West Belmar Elementary School

    • Awarded to Catel Inc
    • Construction: June 2024 – August 29, 2024
    • Construction Update:
      • Close out documents received and in review. 

    Interior Alterations at Multiple Schools (Bid 1 – Toilets)

    • Awarded to Catel Inc.
    • Construction Phase 1: June 2024 – August 29, 2024
      • Wall High School, West Belmar Elementary School, Wall Primary School
    • Construction Phase 2: June 2025 – August 28, 2025
      • Allenwood Elementary School, Central Elementary School, Old Mill Elementary School
    • Construction Update:
      • Punch List issued for Wall High School, West Belmar Elementary School and Wall Primary School.
      • Punch List work in progress.
      • Window Installation for Wall Primary School in progress. Balance of work to occur over Winter Break or other school holiday.

    Interior Alterations at Multiple Schools (Bid 2 - WHS and WIS Educational Spaces)

    • Project Awarded to The Bennett Company
    • Phase 1: HS Auditorium and WIS Locker Room Construction: May 1, 2025 to August 29, 2025
    • Phase 2: HS and WIS Art/Tech Classrooms: June 16, 2025 to August 29, 2025
    • Construction Update:
      • Spiezle issued Notice to Proceed to Bennett on October 23, 2024
      • Permit Drawings submitted to local code office and under review.
      • Code comments responded to on December 2, 2024
      • Preconstruction meeting occurred on December 3, 2024 

    HVAC Upgrades at Allenwood ES, Old Mill ES and West Belmar ES

    • Project Awarded to Kappa Construction
    • Construction: June 2025 – August 2025
      • Phase 1: West Belmar Electrical Feeds: July 2024 – In coordination with Catel Inc.
      • Phase 2: Boiler Work: June 1, 2025 to September 27, 2025
      • Phase 3: Balance of Work: June 16, 2025 to August 29, 2025
    •  Construction Update:
      • Phase 1 work is complete.
      • No new PCOs have been received. 

    HVAC Upgrades at Wall IS, Central ES and Wall High School 

    • Project Awarded to Preferred Mechanical
    • Construction: June 2025 – August 2025
      • Phase 1: Central School Boilers – June 2, 2025 to September 26, 2025
      • Phase 2: Balance of Work – June 16, 2025 to August 29, 2025
    • Construction Update:
      • Spiezle issued Notice to Proceed to Preferred on December 2, 2024
      • Permit Drawings submitted to local code office and under review.
      • Preconstruction Meeting occurred on December 3, 2024 

    Roofing Replacement at Multiple Schools 

    • Project awarded to Pravco Inc.
    • Substantial Completion Date: August 30, 2024
    • Construction update
      • Work is substantially complete and Spiezle has issued punch lists for the work.
      • Tremco issued their final punch list items on October 22, 2024.
      • Final Punch list verification is tentatively scheduled for the week of November 11 

    Athletic Field Upgrades at Wall High School

    • Bidding: February/March 2025
    • Award: March/April 2025
    • Construction: Summer 2025 to Fall 2025
    • Status Update:
      • Schematic documents submitted to district and reviewed on November 27, 2024
      • Community Committee Meeting presentation discussion was held on December 2, 2024 

    Roofing Replacement at Wall HS and Old Mill ES

    • Design: July to October 2025
    • Bidding: November 2025
    • Award: December 2025
    • Construction: June 2026 – August 2026